As a way of keeping the community informed about the overall
progress on the Alton Road construction project, below is a summary of the work
within active zones, the tasks that have been completed and the upcoming
project milestones. This project, which began in April 2013, is scheduled
through the summer of 2015 and has an estimated cost of $32 million. These
overall updates, in addition to the weekly emails, will continue to be sent
throughout the project. Please let us know what additional information would be
helpful during this time as we continue to look for new ways of keeping the
lines of communication open.
Ongoing/Completed Work:
·
Flyover bridge
o Work remains on
schedule
o Contractor has
demolished and removed the traffic railing on either side of the bridge
o Contractor has
started forming the framework for the new traffic railing
o Coordination
continues with the City of Miami Beach Police Department to support the
signalization operations on 5 Street from Alton Road to the east
·
New water main
o From north of 20
Street to 13 Street: The water main has been installed, tested and the
final section is being prepared to be placed into service. The contractor has
also installed new fire hydrants in this area.
o From 13 Street to
6 Street: The contractor is scheduled to continue with water main
installation along the southbound right lane and parking lane of Alton Road by
mid-August
§ A traffic shift will be used to
provide room for the contractor to work. The on-street parking on the east side
of the street will be temporarily removed. On-street parking on the west side
will be maintained where possible – a white bag over a meter means the parking
space is available.
·
Work zone from 17 Street to Michigan Avenue
o From Dade
Boulevard to Michigan Avenue: The contractor continues installing drainage
structures and pipe, as well as installing the foundations for new traffic
signals and street lights. Within the next month, the contractor will begin
rebuilding the roadway and then sidewalk.
o From 17 Street to
Dade Boulevard: The contractor has demolished the roadway. Within the next
week, the contractor will begin installing drainage structures and pipe.
o Once the work is
complete on the east side of the roadway, the contractor will switch to the
west side in the same area. The detour route will remain in place until both
sides of the road are complete.
Next Steps:
·
Restriping West Avenue
o The contractor is
currently scheduled to restripe West Avenue in early September. The restriping
would provide two southbound lanes on and one northbound lane on West Avenue.
·
Implementing the new roadway alternative
o The Department will
continue the process of revising the plans to include wider sidewalks.
o A Public Hearing is
being scheduled for October to present the raised center median concept to the
community and allow for feedback.
PLEASE NOTE THAT THIS SCHEDULE MAY CHANGE DUE TO
WEATHER OR UNEXPECTED CONDITIONS.
The Department will continue its coordination with the
public, City of Miami Beach staff and elected officials. We welcome your
feedback and thank you for your patience during this construction project.
Additional information is available on the project page of
the Department's website.
You may also contact Construction Public Information Specialist Heather Leslie
at 305-905-5876 or email her at Heather@hmlpublicoutreach.com.
Drivers are encouraged to call 511 before they drive, or log onto www.fl511.com to get real-time traffic and lane
closure information.